Answer:
It is advisable to use water-based and solid-state waterproofing coating materials. In planning the construction, the following points should be taken into consideration:
- The main purpose of this type of waterproofing is to prevent rainwater from flowing out of the flowerbed and to help prevent white birch from drying out; it is not the same as the structural waterproofing of the building structure. Therefore, structural waterproofing must comply with the standard construction specifications for courtyards and roofs: it is advisable to use a PU-based or baked-in waterproofing material.
- In the construction process, all brick joints must first be filled and leveled manually (the filling material should be waterproof mortar or acrylic resin mortar).
- After the water-proofing materials are applied and cured, they should be finished and then handed over to the cement workers for primer painting; the work should not be reversed.
- Common mistakes made in construction sites are: first applying a primer and then having the waterproofing contractor complete the work; this type of construction method has a very high failure rate—the waterproofing material applied to the surface often results in subsequent problems such as peeling, poor adhesion, or swelling due to poor quality of the primer layer.
- There are often cracks at the intersection of the bottom of the brick wall and the floor surface, so special attention should be paid before applying the waterproofing coating; it is best to first reinforce the area using a diagonal method.