(One Hundred Questions on Waterproofing) #100: Currently, there are a growing number of cases on the market offering a "10-year warranty for waterproofness". Will this increase the burden on builders and developers significantly?

Answer: Actually, no! Because the cost of waterproofing work only accounts for 1% of the overall construction cost! Taking into account the current selling price of mainstream floor area in Taipei City – 40 square meters, the average selling price is as high as 4 […]

(One Hundred Questions on Waterproofing) Part #97 covers the design of double walls in basements, which may affect the usable floor area of the basement. The water-conducting wall method was developed in response to this need. What material is it made of? What are the standard construction specifications?

A: To achieve the dual function of drainage for the basement walls while not affecting the space for flat parking, water-conducting panels and diamond-shaped meshes are laid on the walls, and the surface is then painted and painted. This is […]

(One Hundred Questions on Waterproofing) In underground basements of #95domestic buildings, there is often a phenomenon of inexhaustible seepage and continuous water leakage. Is there an advanced waterproof material or construction method that can achieve a permanent waterproof function?

Answer: (i) Waterproofing of continuous walls has significant differences in basic design and construction concepts, both domestically and internationally. In foreign countries, continuous walls are defined as the hypothetical construction of retaining walls, […]

(One Hundred Questions on Waterproofing) #93Underground waterproofing can be divided into external waterproofing (external construction) and internal waterproofing (internal construction). What are the different types of external waterproofing methods? What are the standard construction specifications?

Answer: It can be divided into: Standard normative construction drawings for the outer waterproof layer construction method: Standard normative construction drawings for the outer waterproof layer construction method:

(One hundred questions on waterproofing) If a water leak occurs in an #87-tank pool, if an internal waterproofing renovation is carried out, would the process be too long and the project too extensive? Is it possible to fix the leak externally and get it done once and for all?

A: If you want to prevent future problems from occurring by performing a leak repair from the outside, there are only two situations where the success rate is higher: As for the leakage caused by the construction seam at the corner, which occurs most often, because it is applied during the construction process, the success rate is higher than 90%.

(One Hundred Questions on Waterproofing) #83: In some cases, the waterproof coating is only applied by brushing with seven-millimeter quartz powder or by buying some waterproof agent at a hardware store; there is no leakage phenomenon. On the other hand, some construction sites use expensive imported materials from Europe and the United States, but they often leak, and repeated repairs are ineffective. Why is that?

Answer: The key lies in the structure of the tank; as question 83 indicates, 90 percent of the water leakage is due to four major defects in the structure; if these defects are addressed beforehand, it’s fine.

(One Hundred Questions on Waterproofing) #81: How does waterproofing in bathrooms and toilets in newly constructed construction sites work? If (a) polyurethane (PU) is used, what is its functional performance? After construction, there is often a phenomenon of residual adhesion (not fully cured); how can this be prevented? (b) Rubberized asphalt (RA) is used; what are its advantages and disadvantages? (One Hundred Questions on Waterproofing) #81

Answer: (i) If PU construction is adopted, the waterproof function of the RC wall is still possible; the only drawback is that the surface cannot be painted or primed; however, for the brickwork part, the surface cannot be painted or primed.

(One hundred questions about waterproofing) There is often a white coating (wall cancer) on the wall #77near the bathroom. Why does it form? If construction is not carried out from within the bathroom, what are the feasibility issues if construction is carried out from the outside wall?

Answer: (i) The water vapor in the bathroom is heavy, while the water vapor outside the bathroom is light. The water vapor in the bathroom is acidic because it combines with the carbon dioxide and carbon monoxide in the air to form acid water […]

(One Hundred Questions About Waterproofing) After the introduction of the #75-thread method for injecting PU foam, what is the reliability of the leak repair using this commonly used method? How reliable is the use of transparent water-repellent agent to repair window frames?

Answer: (i) Although this method of construction has the advantages of being quick and low-polluting, it also has the following blind spots in terms of actual results: (1) The construction workers must have a thorough understanding of the techniques involved; (2) The quality of the finished product is not guaranteed; (3) The cost of the construction is higher than that of traditional construction methods.

(One Hundred Questions on Waterproofing) #73: Is it possible to waterproof new construction window frames using water-based acrylic waterproofing paint? If there is sufficient budget for high-end luxury homes, what is the most durable and best waterproofing method?

Answer: (i) Using water-based vulcanized asphalt paint to waterproof window frames: based on experience, this black waterproof adhesive (which is also called “water-based PU” on the market, but in fact is a water-based adhesive) has a good waterproof effect.

(One Hundred Questions on Waterproofing) #70Generally, new construction sites will install waterproofed groove for windows and doors. However, contractors are strictly required to apply waterproof agent during construction. Why is there still a frequent occurrence of water leakage? How can it be prevented?

Answer: (i) The author believes that the problem of waterproofed window and door frames is a very important aspect of the construction process (have you noticed that with every typhoon or consecutive heavy rain, how many buildings are damaged or destroyed?).