(One hundred questions about waterproofing)#55 Can the waterproofing in the courtyard be done after the flowerbed tiles are installed and the overall structure is complete? Why?
Answer: Not advisable. Waterproofing should be applied directly to the original structure; the waterproofing of the courtyard should be fully integrated, so it is best to first apply the overall waterproofing of the courtyard floor, and only after that to apply the flowerbed or